(September 2009 – Northern Ireland)
Cable Landing Station for project Kelvin:
- 4x40Ft-container built together = 100m² Telecom room
- 2x generator 200 kVA
- -48Vdc modular redundant system 110kW
- 9000 Ah back up batteries
- Modular inverter -48Vdc/230Vac-20kVA
- DC-distribution racks A& B-feed
- 6+1 HVAC 15kW Redundant cooling system
- Access Control & Intrusion detection
- Fire detection & suppression
- Remote Alarm Monitoring